October Update
Posted October 5th, 2010 by evanjoseAs you can see a great deal of work has been accomplished during the summer. You will now see that construction crews have the decking in place that will be used to form the 4th floor. Some quick highlights from the project:
- Running water: Some people have noticed what seems to be a water leak inside of the building. Believe it or not this is intentional. Allowing water to run over the newly poured concrete helps the concrete cure without cracking. Many of the floors throughout the building will left as exposed polished concrete, so it’s important that we start out right!
- Building name: Early this spring a committee comprised of representatives from UHDS and INTO-OSU met to discuss possible names for the new building. The committee has nearly completed its work and we are hoping that a name will be approved and annouced within the next several weeks.
- Sustainability: While the project team has decided not to pursue LEED certification though the United States Green Building Council (USGBC), the building is implementing a variety of sustainability measures that will be equivalent to USGBC’s LEED Gold rating.
As work progresses, we’ll be sure to post another update. Please feel free to post any comments or questions about the project.