Foundation work
Posted June 8th, 2010 by evanjoseThis week construction crews will be hard at work to prepare for the pouring of the foundation. Critical tasks include running all of the utilities (water, electricity, sanitary) that will need to come up through the concrete slab to service multiple areas of the building, forming the concrete reinforcements, and installing temporary water and electrical service to the building site. To ensure that we meet our construction milestones, crews will be working this Saturday (6/12/2010). None of the construction related activities are expected to have an impact on this weekend’s graduation events.
Monday: (7:30am – 4:30pm)
- – Installation of curb and gutter on 16th & A Ave. (Pacific Excavation)
- – Installation of construction site temp. water and power on site (Berg Electric and Alliant Systems)
- – Building foundation excavation (excavator, rock trucks, front-end loader & compactor)
- – Building survey & layout (Cole Surveying, Marion, Fortis)
- – Form/Rebar/Place building foundation concrete (Marion, concrete & pump trucks
Tuesday: (7:30am – 4:30pm)
- – Installation of curb and gutter on 16th & A Ave. (Pacific Excavation)
- – Installation of construction site temp. water and power on site (Berg Electric and Alliant Systems)
- – Building foundation excavation (excavator, rock trucks, front-end loader & compactor)
- – Building survey & layout (Cole Surveying, Marion, Fortis)
- – Form/Rebar/Place building foundation concrete (Marion, concrete & pump trucks)
Wednesday: (7:30am – 4:30pm)
- – Installation of curb and gutter on 16th & A Ave. (Pacific Excavation)
- – Installation of construction site temp. water and power on site (Berg Electric and Alliant Systems)
- – Installation of construction trailers (level & anchor foundations & hook-up utilities)
- – Installation of new telco, electrical conduits and SW mechanical room vault (Berg Electric)
- – Building foundation excavation (excavator, rock trucks, front-end loader & compactor)
- – Building survey & layout (Cole Surveying, Marion, Fortis)
- – Form/Rebar/Place building foundation concrete (Marion, concrete & pump trucks)
- – Backfill new building foundations (Pacific Excavation)
Thursday: (7:30am – 4:30pm)
- – Installation of curb and gutter on 16th & A Ave. (Pacific Excavation)
- – Prep and pave AC on on Western Blvd. (City of Corvallis, weather pending)
- – Installation of construction site temp. water and power on site (Berg Electric and Alliant Systems)
- – Installation of new telco, electrical conduits and SW mechanical room vault (Berg Electric)
- – Building foundation excavation (excavator, rock trucks, front-end loader & compactor)
- – Building survey & layout (Cole Surveying, Marion, Fortis)
- – Form/Rebar/Place building foundation concrete (Marion, concrete & pump trucks)
- – Backfill new building foundations (Pacific Excavation)
- – Installation of underslab MEP utilities (Berg Electric and Alliant Systems)
Friday: (7:30am – 4:30pm)
- – Installation of curb and gutter on 16th & A Ave. (Pacific Excavation)
- – Prep and pave AC on on Western Blvd. (City of Corvallis, weather pending)
- – Installation of construction site temp. water and power on site (Berg Electric and Alliant Systems)
- – Installation of new telco, electrical conduits and SW mechanical room vault (Berg Electric)
- – Building foundation excavation (excavator, rock trucks, front-end loader & compactor)
- – Building survey & layout (Cole Surveying, Marion, Fortis)
- – Form/Rebar/Place building foundation concrete (Marion, concrete & pump trucks)
- – Backfill new building foundations (Pacific Excavation)
- – Installation of underslab MEP utilities (Berg Electric and Alliant Systems)
Saturday: (7:30am – 4:30pm)
- Building foundation excavation (excavator, rock trucks, front-end loader & compactor)
- Building survey & layout (Cole Surveying, Marion, Fortis)
- Form building foundations (Marion)
- Backfill new building foundations (Pacific Excavation)