Construction Update 5/10
Posted May 10th, 2010 by evanjoseSignificant Impact(s):
- Limited parking on 17th street (see below for details)
- Traffic control revisions on Western between 16th & 17th
- Equipment Noise.
Monday: (7:30am – 4:30pm)
- Flaggers & traffic control on Western to sawcut/prep/pour-back for new AC paving patch (sawcutter & AC Paving trucks/equipment)
- Fill-in & compact foundations at A Ave future parking area where old houses were demo’d (track hoe and back hoe)
- Construct street section on 16th and A (track hoe, back hoe & rock trucks)
- Survey & layout for site electrical re-route work
Tuesday: (7:30am – 4:30pm)
- Flaggers & traffic control on Western for City Water to rework water line (track hoe for digging and back hoe for compaction),
- Fill-in & compact foundations at A Ave future parking area where old houses were demo’d (track hoe and back hoe),
- Construct street section on 16th and A (track hoe, back hoe & rock trucks)
Wednesday: (7:30am – 4:30pm)
- Flaggers & traffic control on Western for City Water to rework water line and Pacific Excavation to rework storm line (track hoe for digging and back hoe for compaction),
- Construct street section on 16th and A (track hoe, back hoe & rock trucks),
- Start work adjacent to Halsell Hall for Pacifc Power trenching and conduit runs (track hoe/back hoe) ***NO STUDENT PARKING ON 17TH NEXT TO HALSELL***
- Build gravel construction entry off 16th (rock trucks, front-end loader & compactor)
Thursday: (7:30am – 4:30pm)
- Flaggers & traffic control on Western for radius curb install at 16th and Western (concrete curb equipment)
- Construct street section on 16th and A (track hoe, back hoe & rock trucks),
- Start work adjacent to Halsell Hall for Pacific Power trenching and conduit runs (track hoe/back hoe) ***NO STUDENT PARKING ON 17TH NEXT TO HALSELL***
- Gas company work at 16th and Western for gas line re-work
- Pacific Power pole removal on 17th
- Level/gravel pad for A Ave future parking area where old houses were demo’d (rock trucks, front-end loader & compactor)
- Building Mass Excavation (track hoe, back hoe, dump trucks)
- New curb install on 16th and A (concrete curb equipment)
Friday: (7:30am – 4:30pm)
- Flaggers & traffic control on Western for AC patch at 16th and Western (AC patch equipment)
- Utility trenching adjacent to Halsell Hall for Pacifc Power trenching and conduit runs (track hoe/back hoe) ***NO STUDENT PARKING ON 17TH NEXT TO HALSELL***
- Gas company work at 16th and Western for gas line re-work
- Level/gravel pad for A Ave future parking area where old houses were demo’d (rock trucks, front-end loader & compactor)
- Building Mass Excavation (track hoe, back hoe, dump trucks)
- New curb install on 16th and A (concrete curb equipment)