The thing about a remodel, is that one thing leads to another. Rarely does a project just require one step.
To get rid of the chimney, first we had to change the heat stove. There was an old, 20 plus year old clunker sitting in one of the main rooms. They told me “no matter what you get, it’s going to be at least 20% more efficient.” What was most significant was being able to vent it directly out the wall, instead of venting up the chimney.
So next it was time to remove the chimney, but once the chimney’s out there will be a hole in the ceiling, so we probably need to plan to re-shingle the roof too.
Thanks to our friend Jack for hanging out with us for several weeks; removing the chimney, stripping the roof and putting on the beautiful new architectural shingles.
So after replacing the heater, removing the chimney, redoing the roof, it was time to finish the interior of the bedroom. Eventually I’d like to vault the ceiling, but for now, just having a soothing bedroom space will do just fine.
thanks so much for this post it gives me some motivation to do the same!